(KTTS News) — Construction gets underway next month on Highway 160 in Nixa.

Crews will build a continuous green ‘T” intersection at Highway 160 and Highway AA; a continuous flow intersection at Highway 160 and Highway CC; and rebuild a bridge over the James River.

Work on the $12.4 million dollar project begins next month and should be finished by 2024.

MoDOT will hold a public meeting Tuesday afternoon from 4:30 p.m. to 6 p.m. at Nixa City Hall.

Press Release

Those interested to learn more about the U.S. Route 160 Intersection Improvements Project at Christian County Routes AA and CC north of Nixa are invited to a public meeting on Tuesday, June 27, the Missouri Department of Transportation said.

The public meeting is scheduled for 4:30-6 p.m. on Tuesday, June 27, at Nixa City Hall, 715 W. Mt. Vernon Street, Nixa. No formal presentation is planned. Those who attend may come at any time between 4:30 p.m. and 6 p.m. to learn about the project and ask questions.

Anyone unable to attend the in-person meeting can view the same exhibits at an online public meeting available at www.modot.org/southwest.

Here’s a look at the project:

  • Construct a continuous green T intersection at U.S. Route 160 and Christian County Route AA
  • Construct a continuous flow intersection at U.S. Route 160 and Christian County Route CC
  • U.S. Route 160 bridge rehabilitation over James River Overflow

Traffic Impacts:

  • Nighttime lane closings on Route 160 at times
  • Narrowed lanes and traffic shifts on Route 160
  • Two lanes open on Route 160 in each direction during daytime hours. Traffic congestion expected on Route 160.
  • Road Closures on Christian County Routes AA and CC

Weather and/or construction delays will alter the work schedule.